Reflection 34: How Do We Prepare for the Unexpected?
This week, we continued to put well-defined processes into practice. Good processes enable the team to clearly see what they are aiming for, while limiting the inevitable surrounding noise and…
Read More
Dropped in to a special heritage project we are involved with to conduct a site health and safety tour with the contractor. Phase 2 is progressing well, Layher modular scaffold and temporary roof erected, slates are stripped, timber and masonry repairs are progressing. Well done team. A good clean, tidy and well managed site.